Sterling Power Plant Cogeneration and Expansion
SCOPE OF SERVICE: Director-level leadership of closing phase of Construction and Post-Construction Claim resolution.
TYPE OF PROJECT: Infrastructure
YEAR: 2010/11
DESCRIPTION: Installation of cogeneration equipment to allow simultaneous production of both electric and thermal energy and allow for future installation of additional power generating capacity.
LOCATION: New Haven, Connecticut
OWNER: Yale University
ARCHITECT: Charney Architects
GENERAL CONTRACTOR: Hunt Construction
BUDGET: $79,000,000